The course calendar provides the schedule for
the course as well as important due dates.
NOTHING is
accepted after the due date. No credit will be given for assignments posted
after the designated time. If you
know you have a conflict with a prior commitment, you must plan to submit your
assignments at an earlier date rather than later. Punctuality and preparedness
are two of the most important skills for a management career...make them
habits NOW!
Spring 2020
WEEK
|
Start Date |
ASSIGNMENTS |
NOTES |
Week
1 |
Jan. 20 |
|
Choose teams |
Week 2 |
Jan. 27 |
Intro to PM Task
Activity Durations |
|
Week 3 |
Feb. 3 |
Forward Pass |
|
Week 4 |
Feb. 10 |
Backward
Pass |
Tuesday, Feb. 18th PRESENTATION DATES, PLACES AND TIMES MUST BE SET!!! |
Week 5 |
Feb. 17 |
Probability
|
Test Review 21
|
Week 6 |
Feb. 24 |
Test
- Tuesday, 25th |
Tuesday 25th Project Management TEST Robotic Activities 1-6 Due Tuesday, March 3 at midnight. Robotic Activity Replies to Classmates due Tuesday, March 10th at midnight.
|
Week 7 |
March 2 |
|
|
Week 8 |
Mar 9 |
THURSDAY: March
12th Project Networks of your
project due. Includes work breakdown structure, estimated times of
completion, the network, ES,LS, EF, LF,, total length of project, critical
path activities.
Email file by midnight Thursday, March 12th.
|
|
Week 9 |
March 16
|
SPRING BREAK
|
|
Week 10 |
Mar 23 |
Decision Support
|
OrganizationalDecisionMaking.pptx
. https://www.youtube.com/watch?v=7Ha34Vu1zZo
|
Week 11 |
March 30 |
Decision Support March 30 Drop Day |
|
Week 12 |
April 6 |
Expert Systems
|
|
Week 13 |
April 13 |
TEST ON THURSDAY
|
THURSDAY,
April 16, ExpertSystems/Decision Support
Test
|
Week 14 |
April 20 |
ARTIFICIAL INTELLIGENCE |
|
Week 15 |
April 27 |
|
|
Week 16 |
May 4 |
TUESDAY GROUP CLASS PRESENTATIONS ON PROJECTS - 15
min. per group
|
Thursday, May 7 ARTIFICIAL INTELLIGENCE TEST
|
|
May
7th
Last Day of Class
Dead Day May 8th GRADUATION - May 16
|